In one highway closure, ADOT completes multiple projects; ADOT avoids future travel delays during US 60 closure for bridge project

Facebooktwitterredditpinterestlinkedinmailby feather

GLOBE – While motorists who routinely travel between Superior and the Globe-Miami area may not know what’s involved with maintaining and repairing the only highway between the communities, they’ve come to know even small projects can mean big travel delays.

  So when the Arizona Department of Transportation planned the most disruptive local project in recent memory – a five-day closure of US 60 for a bridge replacement project – work crews planned ahead to take advantage of a nearly traffic-free road.

  From the time the highway closed late Sept. 12 to when it reopened midday Sept. 17, ADOT maintenance crews based in Superior and Globe spread out across the roughly 15-mile closure to take on multiple maintenance and repair projects at the same time.

  Nearly all the work along this two-lane highway, which cuts through rugged terrain and lacks shoulders in many areas, would have required lane restrictions and delays for the safety of work crews and the public. With the public off the roadway, crews could perform all kinds of work more quickly and more safely than when sharing the road with traffic.

  Best of all, the work means ADOT – and drivers – will avoid multiple future projects that would require disruptive restrictions or even closures.

  ADOT crews performed work on and off the highway over five days. The most visible improvement was a chip seal project that started at Top-of-the-World and extended 4 miles to the east.

  Other work included:

• Repairing damage from this summer’s Telegraph Fire, which burned along miles of US 60
• Removing rocks at risk of falling onto the highway
• Trimming and removing vegetation that was blocking sight lines, uprooting rocks or at risk of falling on the road
• Cleaning drainage systems to prevent flood damage
• Installing conduit in the Queen Creek Tunnel for a future fiber optic cable project
  ADOT coordinated the work with Ames Construction, which required the highway closure as the contractor on the $22.7 million Pinto Creek Bridge replacement project. ADOT crews needed to ensure Ames had constant use of US 60 to access the project site, where crews realigned US 60 to the newly completed bridge at Pinto Creek.

  While traffic began using the new bridge Sept. 17, the project will extend through 2021 as crews remove the old structure and restore the project site to its natural state. More information about the project is available at azdot.gov/PintoCreekBridge.

ADOT works to improve sight lines by removing vegetation along US 60 between Superior and Miami. Photos courtesy Arizona Department of Transportation or ADOT

admin (8146 Posts)


Facebooktwitterby feather
Facebooktwitterredditpinterestlinkedinmailby feather

Comments are closed.

  • Additional Stories

    Residents Oppose Planned Private School

    April 29th, 2024
    by

    As you are aware the house located on 118 Griffin Rd. (Parcel 301-42-062C) is being renovated by Jeremi Brewer for […]


    Young writer wins county award

    April 29th, 2024
    by

      The Ray Elementary School would like to recognize Kindergarten student, Riley Morrison. Riley competed in the Pinal County Juvenile Court […]


    Lobos ranked first in region, fourth in 1A division

    April 26th, 2024
    by

    By Nathaniel A. Lopez   It was a busy schedule for the Lady Lobo softball team last week. They began […]


    Lobos ranked first in region, fourth in 1A division

    April 26th, 2024
    by

    By Nathaniel A. Lopez   It was a busy schedule for the Lady Lobo softball team last week. They began […]


  • Additional Stories

    Heat Proofing Your Garden

    April 24th, 2024
    by

      By Bob Allen SE Pinal County Master Gardener     When Deborah North returned to Arizona from the very […]


    Free financial workshop series offered at Superior Library

    April 24th, 2024
    by

      A free financial security workshop series titled Building Financial Security will be taught at Superior Public Library, 99 Kellner […]


    CASA of Gila County welcomes three new Court Appointed Special Advocates for Gila County Children; The need for volunteers continues to rise

    April 24th, 2024
    by

      In April 2024, CASA of Gila County welcomed three new Court Appointed Special Advocates dedicated to serving the Gila […]


    Growing food in rough terrain – Agro-forest at Arboretum

    April 24th, 2024
    by

        The history of the Boyce Thompson Arboretum and mission developed by its founder Col. Boyce Thompson was to […]


  • Copperarea

  • Southeast Valley Ledger