New US 60 bridge at Pinto Creek opens to traffic; wider structure replaces 72-year old bridge between Superior, Miami

Facebooktwitterredditpinterestlinkedinmailby feather

  A new US 60 bridge over Pinto Creek opened to traffic Friday, Sept. 17, replacing a 72-year-old structure on the only route between Superior and the Globe-Miami area.

  The Arizona Department of Transportation began the $22.7 million bridge replacement project 23 months ago, constructing the new bridge just feet away from traffic that continued using the existing structure. Then on the night of Sunday, Sept. 12, work crews closed US 60 between Superior and Miami for a round-the-clock operation to realign the roadway to the new bridge.

  The 695.5-foot-long bridge opened to the public shortly before noon Friday. While both bridges were designed for two lanes of traffic, the new structure also features 8-foot-wide shoulders and can handle heavier loads.

  “US 60 is a critical route for passenger vehicles and commercial traffic, including heavy loads from mines in the area,” said ADOT Southeast District Engineer Bill Harmon. “By completing this new bridge at Pinto Creek, we’re making sure the highway will remain reliable and safe for decades to come.”

  The bridge is expected to handle roughly 7,200 vehicles a day.

  While the largest milestone of the project is complete, drivers should expect periodic lane restrictions and delays in the area through the rest of 2021. Crews will work to restore the project site to its natural state over the next several months, with work beginning shortly to remove the existing bridge.

  The old bridge, opened in 1949 with an estimated lifespan of 50 years, remained safe for traffic but had reached the end of its useful life. As noted on plaques at each end of the structure, the American Institute of Steel Construction bestowed an annual award of merit for 1949’s Most Beautiful Steel Bridge, Class II. Days after closing the old bridge, crews removed the plaques so they can be donated to local historical societies.

  More information about the project is available at azdot.gov/PintoCreekBridge.

Caption:

Pinto Creek Bridge now open for traffic. Photos courtesy ADOT
admin (7852 Posts)


Facebooktwitterredditpinterestlinkedinmailby feather
Facebooktwitterby feather

Comments are closed.

  • Additional Stories

    Hayden, San Manuel to each host first round of playoffs Friday

    October 21st, 2021
    by

      Hayden High School and San Manuel High School, both being the higher seeds in their playoff matches, will host first […]


    Hayden shuts out Bearcats, 68-0

    October 8th, 2021
    by

      On Friday, October 1, the Hayden Lobos met with the Ray Bearcats underneath the lights of the Ray High […]


    Support Local: Family First Pregnancy Care Center and Family Diaper Bank

    October 6th, 2021
    by

    In April 2020, COVID-19 brought much of Arizona’s economy to a screeching halt. All businesses not deemed “essential” were ordered […]


    Hayden shuts out Bearcats, 68-0

    October 6th, 2021
    by

    By Nathaniel A. Lopez Copper Basin News   On Friday, October 1, the Hayden Lobos met with the Ray Bearcats […]


  • Additional Stories

    Lonny Lloyd McNavage

    October 6th, 2021
    by

      Lonny Lloyd McNavage passed away on Friday, Sept. 24, at his residence in Kearny, Arizona.  Lonny was born to […]


    Kearny Police Report – October 6, 2021

    October 6th, 2021
    by

        Items are given to the Copper Basin News by the Kearny Police Department and reflect information available at the […]


    Copper Town Days celebration and car show set for Oct. 9

    October 6th, 2021
    by

      Year after year, for nine years, October has been a time for fun-seeking locals, as well as visitors pouring […]


    Upcoming shred event for Superior

    October 6th, 2021
    by

      Pinal County Attorney Kent Volkmer, Superior Chamber of Commerce and AARP of Arizona Office would like to advise the […]


  • Copperarea

  • Southeast Valley Ledger