In one highway closure, ADOT completes multiple projects; ADOT avoids future travel delays during US 60 closure for bridge project

Facebooktwitterredditpinterestlinkedinmailby feather

GLOBE – While motorists who routinely travel between Superior and the Globe-Miami area may not know what’s involved with maintaining and repairing the only highway between the communities, they’ve come to know even small projects can mean big travel delays.

  So when the Arizona Department of Transportation planned the most disruptive local project in recent memory – a five-day closure of US 60 for a bridge replacement project – work crews planned ahead to take advantage of a nearly traffic-free road.

  From the time the highway closed late Sept. 12 to when it reopened midday Sept. 17, ADOT maintenance crews based in Superior and Globe spread out across the roughly 15-mile closure to take on multiple maintenance and repair projects at the same time.

  Nearly all the work along this two-lane highway, which cuts through rugged terrain and lacks shoulders in many areas, would have required lane restrictions and delays for the safety of work crews and the public. With the public off the roadway, crews could perform all kinds of work more quickly and more safely than when sharing the road with traffic.

  Best of all, the work means ADOT – and drivers – will avoid multiple future projects that would require disruptive restrictions or even closures.

  ADOT crews performed work on and off the highway over five days. The most visible improvement was a chip seal project that started at Top-of-the-World and extended 4 miles to the east.

  Other work included:

• Repairing damage from this summer’s Telegraph Fire, which burned along miles of US 60
• Removing rocks at risk of falling onto the highway
• Trimming and removing vegetation that was blocking sight lines, uprooting rocks or at risk of falling on the road
• Cleaning drainage systems to prevent flood damage
• Installing conduit in the Queen Creek Tunnel for a future fiber optic cable project
  ADOT coordinated the work with Ames Construction, which required the highway closure as the contractor on the $22.7 million Pinto Creek Bridge replacement project. ADOT crews needed to ensure Ames had constant use of US 60 to access the project site, where crews realigned US 60 to the newly completed bridge at Pinto Creek.

  While traffic began using the new bridge Sept. 17, the project will extend through 2021 as crews remove the old structure and restore the project site to its natural state. More information about the project is available at azdot.gov/PintoCreekBridge.

ADOT works to improve sight lines by removing vegetation along US 60 between Superior and Miami. Photos courtesy Arizona Department of Transportation or ADOT

admin (8003 Posts)


Facebooktwitterby feather
Facebooktwitterredditpinterestlinkedinmailby feather

Comments are closed.

  • Additional Stories

    Support Local: Kearny Elks #2478

    July 13th, 2022
    by

    In April 2020, COVID-19 brought much of Arizona’s economy to a screeching halt. All businesses not deemed “essential” were ordered […]


    July is Make a Difference for Children Month

    July 13th, 2022
    by

      (Gila County, AZ –) Volunteers are needed to make a difference for local youth placed in foster care.  The […]


    Pinal Board of Supervisors approve election for transportation tax

    July 13th, 2022
    by

      The Pinal County Board of Supervisors voted last week to approve calling an election to allow the voters of […]


    Sen. Kelly touts funding for public safety in Pinal County with law enforcement, local officials; Kelly secures $187,000 for Pinal County Operations Center in this year’s federal funding bill

    July 13th, 2022
    by

        Last week, Arizona Senator Mark Kelly visited the Pinal County Emergency Operations Center which will receive $187,000 from […]


  • Additional Stories

    Rudy G. Lujan running for Copper Corridor Justice of the Peace

    July 13th, 2022
    by

      Rudy Lujan is a native Arizonan, growing up in Tucson, AZ and attending Santa Cruz Catholic Elementary School and […]


    Municipal Elections for 2022 across the Copper Corridor: Pinal County made errors on Superior, Mammoth ballots

    July 13th, 2022
    by

     Arizona voters, televisions, radios, and mailboxes are all starting to be consumed by information from candidates in the upcoming primary […]


    Board of Supervisors Approve Solution to Early Ballot Errors in Seven Municipalities

    July 13th, 2022
    by

    At a Special Board of Supervisors Meeting on Tuesday afternoon, the Board approved a definitive solution to the errors found […]


    Pinal County Sheriff’s Office searching for murder suspect

    July 7th, 2022
    by

      On July 4, 2022, at approximately 9:40 p.m., Pinal County Sheriff’s Office received a 911 call regarding shots fired […]


  • Copperarea

  • Southeast Valley Ledger