Long awaited completion of the Kelvin Bridge Replacement Project finally here after 20 years of effort

Facebooktwitterredditpinterestlinkedinmailby feather

Interesting juxtaposition of the new vs the old Kelvin Bridge.

FLORENCE, AZ – – A bridge that has been in use for over 100 years is nearing the end of having to see vehicular traffic travel over it on a daily basis.

  The Kelvin Bridge was built in 1916. The single lane bridge has served the Kelvin/Riverside area for 102 years spanning the Gila River and connecting the eastern side of Pinal County to the central portion.

  “For some people, the Florence/Kelvin Highway is the more convenient way to travel east to west in Pinal County,” said District 1 Supervisor Pete Rios. “This bridge is a necessity for the residents in the area.”

   The objective of the Kelvin Bridge Replacement project is to replace the existing bridge with a 2 lane overpass bridge to not only span the Gila River but the existing ASARCO-Copper Basin Railway as well. The existing 1916 bridge will be repurposed to a pedestrian/equestrian bridge only.

Under construction.

  Almost two decades ago, Pinal County began to pursue federal funding to replace the antiquated Kelvin Bridge. The process for meeting federal funding requirements and the development of construction documents to build the new bridge began in 1998. When federal funds are used in transportation projects, there are specific requirements for environmental, right of way acquisition, utility clearances and the way construction is handled. 

  “This was a labor of love for Joe Ortiz, who, along with other employees throughout the years, worked on getting the approvals,” stated Public Works Director Louis Andersen. “It was a matter of patience, time and filling out stacks of paperwork to just get this project on the radar for the County. I applaud Ortiz’s dedication to getting this bridge going from an idea to reality.”

  An archaeological survey completed in the end of 2007 found deposits and features that necessitated additional data recovery. Archaeologists excavated the features to map, sample and collect artifacts along with curation of the findings. The process began in the spring of 2008 with curation completed with the Arizona State Museum in Tucson in 2013.

  After several years of land research and negotiations Bureau of Land Management issued an environmental clearance in 2012 and the Right-of-Way Amendment Grant in September 2016 which cleared the area for construction of the bridge and associated improvements.

Kelvin Bridge

  The County coordinated with the ASARCO and the Copper Basin Railway to generate an agreement for the improvements at the railroad crossing.

  “At the end of 20 years of work, we have a bridge that will last the next hundred years,” Supervisor Rios said. “I am pleased that everyone worked together to make this project a success. I think it’s a testament to the hard working attitude and determination of our county employees that made two decades of paperwork, phone calls, emails and meetings into a new Kelvin Bridge.”

  There will be a ribbon-cutting ceremony for the Kelvin Bridge on Friday, June 8 at 9:30 a.m. The public is invited to attend the ceremony.

Staff (5795 Posts)

There are news or informational items frequently written by staff or submitted to the Copper Basin News, San Manuel Miner, Superior Sun, Pinal Nugget or Oracle Towne Crier for inclusion in our print or digital products. These items are not credited with an author.


Facebooktwitterby feather
Facebooktwitterredditpinterestlinkedinmailby feather

Comments are closed.

  • Additional Stories

    Annual San Manuel Copper Classic motorcycle race returns March 9

    February 4th, 2024
    by

        Well, they will be at it again. The Trail Riders of Southern Arizona (TRS) will be hosting the […]


    Strong Start to Superior’s 2024

    February 4th, 2024
    by

    Our great town has entered 2024 at hypersonic speed, and we are excited about the many major milestones we have […]


    Winkelman Preparatory Academy plans expansion

    February 4th, 2024
    by

    By Mila Besich   When the school year first started in August of 2023, 16 young girls began attending the […]


    New welding facility open for regional learning in Superior

    February 4th, 2024
    by

      By Nathaniel A. Lopez   It’s official.   On Jan. 23, members of Superior Town Council, Rebuild Superior, Resolution […]


  • Additional Stories

    Queen Creek Bridge replacement project begins on US60; full closures will be required between Superior, Miami for blasting

    February 4th, 2024
    by

      SUPERIOR – The Arizona Department of Transportation is replacing two bridges on US 60 east of Superior with spans […]


    Pinal County hosts vaccine clinics in Kearny, Mammoth

    February 4th, 2024
    by

        On Jan. 14, the Pinal County Animal Care and Control offered low-cost vaccines to local pet owners in […]


    OWN Oracle to disband; Oracle Visitors Center to close

    February 4th, 2024
    by

      By Nathaniel A. Lopez   After many years of service in the Oracle, and surrounding communities, OWN-Oracle Women’s Network, […]


    LOST’s 2024 Hashbrowns, History and Hiking events scheduled

    February 1st, 2024
    by

      The Legends of Superior Trails Inc (LOST). has announced the schedule for its upcoming 2024 Hashbrowns, History and Hiking […]


  • Copperarea

  • Southeast Valley Ledger